SAP PS Transaction Codes Cheat Sheet (by Project Phase)

SAP

October 22, 2026

Quick Answer

The most used SAP PS transaction codes are CJ20N (Project Builder) for building projects, CJ40 and CJR2 for cost planning, CJ30 and CJ32 for budgets, CN25 for confirmations, CJ88 and CJ8G for settlement, and CN41N and CJI3 for reporting. This cheat sheet groups the standard SAP Project System transactions by project phase, so you can find the right one for the job in front of you. It also lists the system statuses that decide what each transaction allows. SaiSatwik consultants use the same grouping when training key users.

How should you use this SAP PS transaction codes cheat sheet?

SAP PS transaction codes make more sense grouped by the stage of a project than in alphabetical order. Each table below covers one phase. All codes listed are standard SAP Project System transactions that run in ECC and SAP S/4HANA.

If you are new to the module, read the SAP PS beginner guide first. It explains the objects these transactions work on. Your system may also have custom Z transactions; check with your SAP team before relying on them.

Which SAP PS transaction codes build the project structure?

Structure transactions create and change project definitions, WBS elements, networks and templates. CJ20N covers almost all of it in one screen, as the CJ20N walkthrough shows.

TransactionPurpose
CJ20NProject Builder: create and change the whole project
CJ06 / CJ07 / CJ08Create, change, display project definition
CJ01 / CJ02 / CJ03Create, change, display work breakdown structure
CJ11 / CJ12 / CJ13Create, change, display WBS element
CN21 / CN22 / CN23Create, change, display network
CJ2B / CJ2CChange, display project planning board
CJ91 / CJ92 / CJ93Create, change, display standard WBS (template)
CN01 / CN02 / CN03Create, change, display standard network (template)
SAP PS structure transactions

Which SAP PS transaction codes handle planning and budgeting?

Planning transactions record expected cost. Budget transactions record approved money. The SAP PS cost planning guide and the guide to budgeting and availability control explain when to use each.

TransactionPurpose
CJ40 / CJ41Change, display overall (structure) cost plan
CJR2 / CJR3Change, display cost element and activity input plan
CJ30 / CJ31Change, display original budget
CJ32 / CJ33Change, display budget release
CJ34Budget transfer between WBS elements or projects
CJBVActivate availability control
CJBNReconstruct availability control
SAP PS planning and budgeting transactions

Which SAP PS transaction codes are used during execution?

Execution transactions record what actually happens on the project: work done, materials needed and deliveries made.

TransactionPurpose
CN25Confirm a network activity
CN27Collective confirmation
MD51Project-driven MRP for one project
CNS0Create delivery from project
SAP PS execution transactions

Which SAP PS transaction codes run the period-end close?

Period-end transactions run in a fixed order: overhead, then results analysis, then settlement. The SAP PS settlement guide and the results analysis guide cover the detail.

TransactionPurpose
CJ44 / CJ45Overhead calculation, individual and collective
KKA2 / KKAJResults analysis, individual and collective
CNE1 / CNE2Progress analysis, individual and collective
CJB2 / CJB1Generate settlement rules, individual and collective
CJ88 / CJ8GSettlement, individual and collective
CJICMaintain line item settlement for assets under construction
SAP PS period-end transactions

Which SAP PS transaction codes are best for reporting?

Reporting transactions are where most users spend their time once a project is live. CN41N alone answers most structure and status questions.

TransactionPurpose
CN41NStructure overview: whole project with dates and statuses
CN42N / CN43NProject definitions and WBS elements overview
CN47NNetwork activities overview
CJI3Actual cost line items
CJI5Commitment line items
S_ALR_87013532Plan, actual, commitment, remaining plan and assigned values
CJE0Run a project hierarchy report
CNE5Progress analysis (earned value) report
SAP PS reporting transactions

CNE5 is the earned value view. The earned value management guide explains how to read it.

Which configuration transaction codes should SAP PS consultants know?

Configuration transactions belong to the SAP team, not end users. These five open the profiles that shape how every project behaves. The SAP PS configuration guide walks through them in order.

TransactionPurpose
OPSAProject profile
OPSJProject coding mask
OPUUNetwork profile
OPS9Budget profile
OKO7Settlement profile
Key SAP PS configuration transactions

Which system statuses decide what SAP PS transactions allow?

Many SAP PS errors are status problems, not transaction problems. A posting fails because the WBS element is still created, not released. These system statuses matter most.

  • CRTD (created). Planning allowed, actual postings blocked.
  • REL (released). Actual postings allowed.
  • BUDG (budgeted). A budget has been entered.
  • SETC (settlement rule created). The object has a settlement rule.
  • TECO (technically completed). Work finished; most new commitments blocked, costs can still post.
  • CLSD (closed). No further postings.

How does SaiSatwik train teams on SAP PS transactions?

SaiSatwik trains SAP PS users by role, not by transaction list. A project administrator learns the structure and reporting codes. A controller learns planning, budgeting and period-end. Training runs on the client’s own project templates, so the first live project looks familiar.

Role-based training is part of every engagement from the SaiSatwik SAP practice. Official reference documentation sits on the SAP Help Portal, and formal courses are on SAP Learning. All the codes here also run in SAP S/4HANA, alongside newer SAP Fiori apps.

FAQs about SAP PS transaction codes

What is the most important SAP PS transaction code?

CJ20N, the Project Builder. It creates and changes project definitions, WBS elements, networks, activities and milestones in one screen. Most project administrators spend more time in CJ20N than in every other SAP PS transaction combined.

Which transaction shows actual costs on a project?

CJI3 lists actual cost line items by project or WBS element. For a summary of plan against actual and commitments, use S_ALR_87013532. CJI5 lists commitment line items such as open purchase orders.

Do SAP PS transaction codes work in SAP S/4HANA?

Yes. The standard SAP PS transactions in this cheat sheet run in SAP S/4HANA. SAP also adds Fiori apps for project monitoring, and some detailed planning moves toward SAP Analytics Cloud.

Why does SAP PS say my WBS element has the wrong status?

The element’s system status forbids the action. New elements sit in CRTD, which blocks actual postings. Release the element in CJ20N, or check whether it is already technically completed or closed.

You May Also Like…

0 Comments

Submit a Comment